Broward County Commission Regular Meeting


Print

Return to the Search Page Return to the Agenda
AI-25155 8.       
Meeting Date: 09/25/2018  
Director's Name: Thomas Hutka
Department: Public Works Division: Highway Const. & Engineering

Information
Requested Action
MOTION TO APPROVE Old Plantation Water Control District Permit No. 1174 allowing Broward County to construct, maintain, and repair traffic signal communications network improvements within Canal No. C2 and Canal No. C3 crossing Broward Boulevard, at a nominal cost of $10 to the County; and authorize Mayor and Clerk to execute same. (Commission Districts 1 and 5)

ACTION:  (T-10:57 AM)  Approved.

VOTE: 9-0.
Why Action is Necessary
Board of County Commissioners' approval is recommended for non-typical permits.
What Action Accomplishes
Allows Broward County to construct, maintain and repair traffic signal communications network improvements for public purposes within the Old Plantation Water Control District’s Canal No. C2 and Canal No. C3 crossing Broward Boulevard.
Is this Action Goal Related
Previous Action Taken
None.
Summary Explanation/Background
PUBLIC WORKS DEPARTMENT/HIGHWAY CONSTRUCTION AND ENGINEERING DIVISION RECOMMENDS APPROVAL.

Broward County is extending the fiber optic traffic signal communications network along Broward Boulevard from University Drive to Flamingo Road in the City of Plantation. This construction project requires crossing the Old Plantation Water Control District's Canal No. C2 and Canal No. C3 along the north side of Broward Boulevard. The C2 crossing will consist of a bridge-mounted conduit and the C3 crossing will be an underground directional bore crossing. The District is agreeable to these canal crossings and requires the use of a permit, rather than a typical revocable license agreement, to provide Broward County with the necessary access.

Approval of the permit by the Board of County Commissioners will allow Broward County to construct, maintain and repair improvements within the District's canals. The permit is a non-exclusive, revocable permit. It includes limitation statements, insurance requirements, and an indemnification provision which are typically included in a revocable license agreement rather than in a permit. The District requires these permit conditions for projects within its canals.

The Old Plantation Water Control District approved this permit in mid-2017. However, it could not be brought to the Board of County Commissioners for approval until the U.S. Army Corps of Engineers (ACOE) issued its permit for the project. ACOE required an extended review and approval period due to the significant backlog in its internal plan review process. The ACOE permit for this project was issued on July 30, 2018 and this permit with the Old Plantation Water Control District is now ready for the Board's consideration and approval.

The permit has been reviewed and approved as to form by the Office of the County Attorney and the Risk Management Division.
Source of Additional Information
Richard C. Tornese, P.E., Director, Highway Construction and Engineering Division, (954) 577-4579
Thomas J. Hutka, P.E., Director, Public Works Department, (954) 357-6410

Fiscal Impact
Fiscal Impact/Cost Summary:
There is no fiscal impact to Broward County.
Attachments
Exhibit 1 - Permit No. 1174
Exhibit 2 - Location Map


    